The thermoelectricity project of the first stage project"2 furnaces and 1 machine" has been finished in December of 2003 and was put into usage. The installed capacity is 15MW and annual energy output reaches to 0.12 billion Kilomatt-hours. It has become the new economic point of growth of the company. It not only greatly cuts the production cost but also brings boon for the employees because it provides good conditions for their life to realize electrization. The second stage project "1 furnace and 1 machine" will start to generate power and run before May of 2004.
 
 